Estimating And Costing MCQ's Test No 04 |
1 Pick up the incorrect statement regarding a master trap from the following: ?
Pick up the incorrect statement regarding a master trap from the following is " The water seal is less than that of ordinary traps "
2 The order of booking dimensions is ?
The order of booking dimensions is " Length, breadth, height "
3 The detention period in a septic tank is assumed ?
The detention period in a septic tank is assumed “30 minutes"
4 height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the
falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by
Prismoidal formula is?
height of the embankment at zero chainage is 0.5 m, the width is 11 m and side slopes 2:1. If the falling gradient of the embankment is 1 in 150, the quantity of the earthwork calculated by Prismoidal formula, is " 3225 m3 "
5 Pick up the item of work not included in the plinth area estimate ?
Pick up the item of work not included in the plinth area estimate is " Courtyard area "
6 The minimum width of a septic tank is taken
The minimum width of a septic tank is taken " 75 cm "
7 The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended, is ?
The diameter of a domestic sewer pipe laid at gradient 1 in 100 is recommended “150 mm "
8 Pick up the item whose weight is added to the weight of respective item, is ?
Pick up the item whose weight is added to the weight of respective item, is " All the above "
9 The unit of measurement is per quintal for the following: ?
The expected out turn for earth work in excavation in ordinary soil per workman per day is ” M.S. reinforcement of R.C.C. works "
10 Pick up the incorrect statement from the following: ?
Pick up the incorrect statement from the following is “ None of these "