Estimating And Costing MCQ's Test No 03



Estimating And Costing MCQ's Test No 03, 1 Size, capacity and materials need be specified for ?  A) Bib-cocks  B) Stop-cocks  C) Ball valves  D) All of the above ... Answer is D ) Size, capacity and materials need be specified for " All of the above " Show Answer 2 The item of steel work which is measured in sq.m, is ?  A) Collapsible gates  B) Rolling shutters  C) Ventilators and glazing  D) All the above ... Answer is D ) The item of steel work which is measured in sq.m, is " All the above " Show Answer 3 The damp proof course (D.P.C.) is measured in ?  A) Cub. m  B) Sq. m  C) Meters  D) None of these ... Answer is B ) The damp proof course (D.P.C.) is measured in “Sq. m" Show Answer 4 The volume is measured correct to the nearest ?  A) 0.03 cum  B) 0.02 cum  C) 0.01 cum  D) 0.04 cum
Estimating And Costing MCQ's Test No 03


1 Size, capacity and materials need be specified for ?




... Answer is D )
Size, capacity and materials need be specified for " All of the above "

2 The item of steel work which is measured in sq.m, is ?




... Answer is D )
The item of steel work which is measured in sq.m, is " All the above "

3 The damp proof course (D.P.C.) is measured in ?




... Answer is B )
The damp proof course (D.P.C.) is measured in “Sq. m"

4 The volume is measured correct to the nearest ?




... Answer is C )
The volume is measured correct to the nearest is " 0.01 cum"

5 The brick work is measured in sq metre, in case of ?




... Answer is D )
The brick work is measured in sq metre, in case of " All the above"

6 The height of the sink of wash basin above floor level is kept




... Answer is C )
The height of the sink of wash basin above floor level is kept is " 75 cm to 80 cm "

7 For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is ?




... Answer is B )
For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is “0.274 m3 "

8 Pick up the item whose weight is added to the weight of respective item, is ?




... Answer is D )
Pick up the item whose weight is added to the weight of respective item, is " All the above "

9 The expected out turn for earth work in excavation in ordinary soil per workman per day is ?




... Answer is C )
The expected out turn for earth work in excavation in ordinary soil per workman per day is ” 3.00 cum "

10 The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, Is ?




... Answer is B )
The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, Is “1.25 m3 "